The project involved the replacement and connection back to an existing suction and discharge pipework on a solvent storage facility in Tottenham. We worked closely with both the client and pump supplier to ensure no disruption to production was caused. All pipework was fabricated and tested to ASME B31.1. Duration on site – 3 weeks.

Click on the images below for more detail.