Here we undertook a five-month site installation of 216No suppression bottles, 54No detectors along with the electrical wiring. The project included site surveys, working with our customer IEP and RWE to agree positions of the equipment that where with design specification and practicable for maintenance.

We designed, fabricated and installed all bracketry for the suppression and detector equipment. The project had to be completed within the allocated shut down period, the project was delivered on time and to budget.